Restaurant licence and approvals in Dubai: authorities, kitchen approvals, delays and fines

SAShashank Ashok Restaurant Marketing 12 min read Last updated
The Dubai skyline along Sheikh Zayed Road

The short answer: a restaurant in mainland Dubai needs a trade licence, Dubai Municipality approval as a food establishment with an assessed kitchen layout, landlord and fire safety approval of the fit-out, a signage permit, and trained, medically cleared staff. A restaurant has more to approve than a café because it cooks with heat, smoke and grease: extraction, fire protection and grease management sit at the centre of the process. Extras such as outdoor seating, shisha, music and alcohol each need their own permission.

General information, not legal or licensing advice. Rules, fees and portals change. Confirm every step with the authority concerned or a licensed adviser. Checked on 19 November 2026.

Key points

  • The hot kitchen drives the approvals: extraction, fire protection and grease trap.
  • Have the kitchen layout assessed before any building work starts.
  • Every food establishment needs a trained, certified Person in Charge.
  • Outdoor seating, shisha, entertainment and alcohol are separate permissions.
  • A team of 20 or more may bring Emiratisation obligations.
  • We found no official published timeline, so plan with a margin.

Who approves what

AreaWho to deal withRestaurant-specific point
Trade licenceDubai Department of Economy and Tourism (DET) on the mainland; the free zone authority in a free zoneThe licence activity must match what you will actually serve and do
Food establishment approvalDubai Municipality, Food Safety DepartmentFull kitchen layout assessment and inspection
Fit-outLandlord, mall or master developer, plus the authority with building controlCooking must be a permitted use of the unit
Fire safetyDubai Civil DefenceKitchen hoods and cooking equipment bring extra fire protection requirements
SignageDET issues trade-name signage permitsOne trade name on the storefront; Arabic above English
Outdoor seatingDubai Municipality guideline, plus landlord consentTerraces are valuable in winter; plan the permission early
ShishaDubai Municipality permitServing without a permit has led to fines and closures
Music, entertainment, eventsDET e-permits systemLive music, DJs and ticketed events
StaffFederal labour and residency authoritiesLarger teams bring more obligations
TaxFederal Tax AuthorityVAT, corporate tax

We could not open the official DET, Civil Defence and DEWA service pages while preparing this guide, so those rows are stated in general terms. We also could not confirm which body currently issues alcohol licences in Dubai, as published sources conflict; ask a licensed adviser if your concept depends on it.

Step 1: The trade licence

The UAE government portal sets out the stages for a mainland business: choosing the activity and legal form, registering the trade name, initial approval, arranging a location, additional government approvals and the licence itself (u.ae). The tenancy is registered through Ejari. UAE law allows 100% foreign ownership of mainland companies in most activities (u.ae), and Dubai applied this to more than 1,000 commercial and industrial activities from 1 June 2021 (Dubai Media Office). Confirm it for your activity.

Almost 1,200 new restaurant licences were issued in Dubai in 2024, according to the Department of Economy and Tourism. We could not confirm official fees; ask for a written quote.

Step 2: Dubai Municipality and the kitchen layout

Licensing a food establishment is subject to Municipality approval (Local Order 11 of 2003), and Dubai Municipality lists a “Request for Layout Assessment for Food Establishment Licensing” service (Dubai Municipality). For a restaurant, the layout is a full commercial kitchen, and it should be assessed before the contractor starts.

We could not open the Municipality’s detailed requirement documents, so no official dimensions are given here. A restaurant layout normally has to show:

  • A one-way flow from goods receiving to storage, preparation, cooking, the pass and service, with dirty returns kept separate.
  • Separate preparation areas or times for raw meat, poultry, fish and ready-to-eat food.
  • Walk-in or reach-in cold storage and dry storage sized to the menu.
  • Extraction hoods over all cooking equipment, with a duct route to the outside.
  • A grease trap sized for the kitchen.
  • Staff handwash basins in each area, separate from food sinks.
  • A wash-up area with pot wash and dishwasher.
  • Cleanable floors, walls and ceilings, and proper drainage.
  • Waste storage, pest control, chemical storage and staff changing space.

Use a kitchen designer who has had restaurant layouts approved in Dubai recently. See kitchen layout, menu and staffing.

Step 3: Fit-out, extraction and fire safety

ItemWhy it matters for a restaurant
Permitted useNot every unit allows cooking. Check the lease and the building rules first
Extraction routeThe duct must reach an approved discharge point, often the roof. No route means no hot kitchen
Fire protectionCooking with grease usually requires a fire suppression system in the hood, plus alarms and extinguishers approved by Civil Defence
GasPiped gas, cylinders or all-electric: each has its own approval and safety requirements
Grease trapNeeds space, access for cleaning and a service contract
Landlord approvalsDrawings, contractor details, insurance, a fit-out deposit and a final inspection
Smoke and smellCharcoal, tandoor and wood-fired cooking may need extra filtration and landlord consent

Ask the landlord for the fit-out guide before signing. It lists the approvals, deposits and timelines for that building.

Step 4: Signage, terrace and extras

  • Signage: DET issues trade-name signage permits and inspects shopfronts under the 2024 Outdoor Advertising Manual. Reported rules include one trade name per storefront and Arabic above English (Khaleej Times, 13 May 2026).
  • Outdoor seating: Dubai Municipality publishes an Outdoor Seating Area Guideline.
  • Shisha: needs a Municipality permit. In 2020 the Municipality reported fining 133 cafés and closing eight, including for serving shisha without a valid permit (Dubai Municipality).
  • Music and events: permits are handled through the DET e-permits system.
  • Ramadan: restaurants continue to operate normally during the day (Khaleej Times, February 2026).

Step 5: Staff rules

  • Person in Charge: every food establishment must appoint a trained, certified PIC (Dubai Municipality).
  • Occupational health card: required for food workers (Local Order 11 of 2003).
  • Health insurance: employers must provide it and may not charge employees (Dubai Law 11 of 2013).
  • Wages: the enhanced Wage Protection System took effect on 1 June 2026, with wages due by the first day of the following month (EY tax alert).
  • Emiratisation: under rules reported in 2023, firms with 20 to 49 staff in 14 sectors, including hospitality, had to employ one UAE national in 2024 and another in 2025, with financial penalties for non-compliance (Gulf News). We did not confirm the rules for 2026 onwards, so check the current position if your team will reach 20.
  • Visas: we could not confirm current official costs. Ask for a written cost per employee.

Step 6: Tax and fees on the bill

ItemWhat the source says
VATMandatory registration threshold AED 375,000 (Federal Tax Authority)
Corporate tax0% up to AED 375,000 of taxable income, 9% above (u.ae)
Municipality feeReduced from 10% to 7% on sales at restaurants and hotels in 2018 (Khaleej Times). It did not apply to every restaurant
2026 reliefA package announced on 21 May 2026 included an exemption from the sales fees on hotel rooms and restaurants for DET-registered establishments (Khaleej Times). Dates were not published in the reports we read

Ask an accountant which of these apply to your licence and location before printing menu prices.

How long does it take, and why it slips

We found no official published timeline. Consultancy websites quote ranges that do not agree. A restaurant generally takes longer than a café because the kitchen is larger and has more to approve. The causes of delay below are what we see and hear from clients, not official figures.

CauseHow to avoid it
No approved extraction routeConfirm the duct route with the landlord in writing before signing
Building started before the layout was assessedAssess first, build second
Menu changed after drawings were submittedFreeze the menu and equipment list before submission
Long-lead kitchen equipmentOrder combi ovens, hoods and cold rooms early
Landlord approvals slower than expectedGet the fit-out guide and timelines before signing
Gas and utility connectionsApply as early as the process allows
Staff visas, health cards and trainingRecruit during the fit-out
Failed inspectionRun a mock inspection with the contractor and Person in Charge

Inspections, fines and closures

FactSource
34,700 food inspection visits in Dubai in the first half of 2025Dubai Municipality
24,820 inspections in the first five months of 2026Gulf News, 8 June 2026
247 food establishments closed in the first half of 2021, 168 of them for food safety violationsGulf News, 13 July 2021
Two mall food-court outlets temporarily shut in 2016 after a cockroach complaintKhaleej Times, 25 August 2016
Fines under the public health order range from AED 100 to AED 500,000; a licence may be suspendedLocal Order 11 of 2003, Article 86
Plans announced for AI-supported food safety checks, including scanning customer reviewsKhaleej Times, 16 November 2026

A newer public health law (Dubai Law 5 of 2025) exists and we could not open its fine schedules, so check the current position. A closure is public and is reported in the press, so the reputational cost is usually larger than the fine.

Staying compliant

  • Daily temperature, cleaning and delivery records.
  • Active pest control, grease trap, hood cleaning and fire system service contracts.
  • Licence, health card and training renewals in a calendar.
  • No new cooking equipment, shisha, terrace seating or sign without its approval.
  • Allergen information kept accurate when the menu changes.

Where Food On Focus fits in

We are a marketing and content agency, not licensing consultants. We work on the brand, menu design, photography, video and launch, planned alongside the fit-out so marketing is ready when approvals arrive. Continue with the systems to set up before opening, or go back to the complete checklist.

Frequently asked questions

What licence do I need to open a restaurant in Dubai?

A trade licence for the restaurant activity, issued on the mainland by the Department of Economy and Tourism or by the free zone authority in a free zone, plus Dubai Municipality approval as a food establishment. Confirm the exact activity and fees with the authority or a licensed adviser.

What approvals does a restaurant kitchen need in Dubai?

A layout assessment by Dubai Municipality, landlord approval of the fit-out, and fire safety approval. Cooking with heat and grease brings extraction, fire protection and grease trap requirements.

Can a foreigner own 100% of a restaurant in Dubai?

UAE law allows 100% foreign ownership of mainland companies in most activities. Confirm it for your specific activity.

How long does it take to open a restaurant in Dubai?

We found no official published timeline. A restaurant generally takes longer than a café because the kitchen is larger. Plan with a margin and do not announce an opening date until approvals are in hand.

Do I need a permit for shisha or outdoor seating in Dubai?

Yes. Shisha needs a Dubai Municipality permit, and Dubai Municipality publishes a guideline for outdoor seating areas. Landlord consent is normally needed too.

What are the fines for food safety violations in Dubai?

Dubai's public health order of 2003 sets fines from AED 100 to AED 500,000 and allows a licence to be suspended. A newer public health law exists, so check the current schedule with Dubai Municipality.

Sources

  1. UAE Government portal: steps to start a business on the mainland
  2. UAE Government portal: full foreign ownership
  3. Dubai Media Office: full ownership procedures (3 June 2021)
  4. Dubai Department of Economy and Tourism: gastronomy industry in 2024 (via Zawya)
  5. Dubai Municipality: information for food establishments
  6. Dubai Local Order 11 of 2003 concerning public health
  7. Dubai Municipality: Person in Charge programme
  8. Dubai Municipality: outdoor seating area guideline
  9. Khaleej Times: shop signage rules (13 May 2026)
  10. Dubai Municipality: shisha café fines (9 August 2020)
  11. Khaleej Times: Ramadan 2026 in Dubai
  12. Dubai Law 11 of 2013: health insurance
  13. EY: enhanced Wage Protection System
  14. Gulf News: Emiratisation for firms with 20 to 49 staff (30 November 2023)
  15. Federal Tax Authority: VAT registration
  16. UAE Government portal: corporate tax
  17. Khaleej Times: Dubai cuts fees on hotels and restaurants (12 June 2018)
  18. Khaleej Times: Dubai economic incentives package (21 May 2026)
  19. Dubai Municipality: food inspections in H1 2025
  20. Gulf News: food inspections in early 2026
  21. Gulf News: food outlet closures in H1 2021
  22. Khaleej Times: food court outlets shut (25 August 2016)
  23. Khaleej Times: AI food safety checks (16 November 2026)
SA

Written by

Shashank Ashok

Co-Founder, Food On Focus Media. Meet the team

Disclaimer: This article shares general guidance based on Food On Focus Media's experience as a Dubai F&B creative agency. It is for information only and is not a substitute for advice tailored to your specific brand, menu or market.