# Cafe Floor Plan, Menu, Staffing and Costs: Planning a Dubai Cafe

> How to plan a new café in Dubai: floor plan zones, menu and item analysis by concept, kitchen and staff needs, utilities and the costs to budget.

Source: https://foodonfocus.com/blog/cafe-floor-plan-menu-and-staffing-dubai/

# Planning a new café in Dubai: floor plan, menu, staffing, utilities and costs
By Shashank Ashok, Co-Founder, Food On Focus Media. Published 14 November 2026.

**The short answer:** decide the menu before the floor plan. What you serve decides the equipment, the equipment decides the kitchen, the kitchen decides how many seats are left, and the seats and menu together decide how many staff you need. Most expensive mistakes in a new café come from doing this in the wrong order: signing a unit, drawing a layout, then discovering the menu does not fit the kitchen.
**Opening a café in Dubai: the series**
- [How to open a café in Dubai: the complete checklist](https://foodonfocus.com/blog/how-to-open-a-cafe-in-dubai/)
- [Licence, approvals, delays and fines](https://foodonfocus.com/blog/cafe-licence-and-approvals-dubai/)
- [Floor plan, menu, staffing and costs](https://foodonfocus.com/blog/cafe-floor-plan-menu-and-staffing-dubai/)
- [POS and ERP, website, delivery apps and Google](https://foodonfocus.com/blog/cafe-pos-erp-website-delivery-google-setup-dubai/)
**Key points**
- Plan in this order: concept, menu, equipment, kitchen, seating, staff.
- Every menu item has a cost in space, equipment, power, prep time and skill.
- Dubai Municipality reviews the kitchen layout, so draw it with the approval in mind.
- Check power, water, drainage, gas and ventilation before you sign a lease.
- Budget for the months before opening and the months after, not only the fit-out.

## Step 1: Fix the concept in one sentence
Write down who it is for, what they come for, and when. “A specialty coffee bar for office workers, busiest from 7am to 11am” leads to a very different unit, menu and team than “a family brunch café, busiest at weekends”.
| Concept | Busiest time | What it needs most |
|---|---|---|
| Specialty coffee bar | Weekday mornings | A fast bar, a small pastry offer, few seats |
| Brunch café | Weekend late mornings | A full kitchen, more seats, more floor staff |
| Bakery café | Mornings and afternoons | Ovens, proofing and display space, early shifts |
| Dessert and cake café | Afternoons and evenings | Display chillers, cold storage, a pastry chef |
| Healthy bowls and juice bar | Lunch and after gym | Cold prep space, blenders, fresh produce storage |
| Grab-and-go and sandwiches | Lunch | Display fridges, a prep kitchen, speed at the till |
| Karak and cafeteria | All day and late | A simple hot line, takeaway window, parking access |

## Step 2: Analyse the menu item by item
Before you finalise a menu, put every item through the same questions. This is the “item analysis” that shows whether the menu fits the space.
| Question | Why it matters |
|---|---|
| What equipment does it need? | Each machine takes space, power and budget |
| Does it need cooking with heat, smoke or grease? | That triggers extraction, fire and grease trap requirements |
| How long does it take to make at peak time? | Slow items block the bar or the pass |
| Which ingredients does it share with other items? | Shared ingredients cut stock, waste and storage |
| What is its shelf life? | Short-life items raise waste unless they sell fast |
| What does it cost to make, and what can it sell for? | This is your margin per item |
| Does it travel? | If not, it cannot go on the delivery apps |
| Who can make it? | A dish only one person can cook is a risk on their day off |
A useful rule: if an item needs its own machine, its own ingredients and its own skilled person, it has to earn its place.

## Step 3: What each type of menu demands
| Menu type | Kitchen and equipment | Staff | Watch out for |
|---|---|---|---|
| Coffee and tea only | Espresso machine, grinders, filter station, ice, fridge | Trained baristas | Water quality and enough power for the machine |
| Coffee plus bought-in pastry | As above, plus display and a small oven for finishing | Baristas, one all-rounder | A reliable supplier and daily ordering |
| Cold food: sandwiches, salads, bowls | Cold prep counters, fridges, a handwash and prep sink | A prep cook | Cold storage space and date labelling |
| Hot brunch: eggs, grills, pancakes | Hob, griddle, extraction hood, fire system, grease trap | A cook and a kitchen helper | Extraction route and landlord approval |
| In-house bakery | Ovens, mixer, proofer, cooling racks, dry storage | A baker, early starts | Heat, power load and floor space |
| Desserts and cakes | Chillers, freezer, pastry bench, display | A pastry chef | Temperature control and display life |
| Juices and smoothies | Blenders, juicers, produce fridges | A juice maker | Noise, cleaning time and fresh stock |
Anything cooked with heat and grease changes the approvals and the fit-out cost. See [licence, approvals, delays and fines](https://foodonfocus.com/blog/cafe-licence-and-approvals-dubai/) for what the authorities look at.

## Step 4: Engineer the menu
Menu engineering is a long-established method of sorting items by how well they sell and how much profit each makes.
| Type | Sells | Profit per item | What to do |
|---|---|---|---|
| Stars | Well | High | Feature them, photograph them, keep them consistent |
| Plough horses | Well | Low | Raise the price slightly, trim the cost or pair with a high-margin add-on |
| Puzzles | Poorly | High | Rename, reposition, photograph or have staff recommend them |
| Dogs | Poorly | Low | Remove, unless they bring in a specific customer |
You will not have sales data before opening, so start with a short menu, track every item from day one, and review after four to six weeks. A short menu also means a smaller kitchen, less stock and faster training.
How the menu is designed matters too: the order of items, the names, the descriptions and which items carry a photo. See our [menu design](https://foodonfocus.com/menu-design-dubai/) service and [how better menu photography increases order value](https://foodonfocus.com/blog/how-better-menu-photography-increase-average-order-value/).

## Step 5: Draw the floor plan around the flow
A café floor plan has two flows that should not cross: the customer’s path and the food’s path.
| Zone | What goes there | Planning notes |
|---|---|---|
| Entrance and queue | Door, menu board, queue line | The menu should be readable before the till |
| Counter and bar | Till, espresso machine, display, pick-up point | Order, pay and collect in one direction |
| Seating | Tables, banquettes, bar stools, outdoor seats | Mix of twos and fours; outdoor seating may need a permit |
| Kitchen and prep | Cooking line, prep counters, pass | Raw and cooked kept apart; a clear route to the pass |
| Wash-up | Sinks, dishwasher, racks | Away from food prep, near the dirty-plate return |
| Storage | Dry store, fridges, freezer, chemicals | Chemicals stored separately from food |
| Staff area | Lockers, changing space | Often forgotten; check what your approvals require |
| Utilities | Electrical panel, water heater, grease trap, gas, AC units | Must stay accessible for maintenance |
| Delivery handover | A shelf or window for riders | Keep riders out of the customer queue |
The kitchen layout is reviewed as part of the food approvals, so it is worth having it drawn by someone who has done café projects in Dubai before. Changes after the fit-out has started are slow and costly.

## Step 6: Check the utilities before you sign the lease
A beautiful unit with the wrong utilities can make a concept impossible. Ask the landlord or agent for these in writing:
| Utility | What to check |
|---|---|
| Electrical load | Is the available power enough for the coffee machine, ovens, fridges and AC together? |
| Water and drainage | Are there supply and drain points where the kitchen and bar will be? |
| Grease trap | Is one installed, or is there space and permission to add one? |
| Kitchen extraction | Is there a route for a hood and duct to the outside or roof? Does the building allow cooking? |
| Gas | Is piped gas available, are cylinders allowed, or must the kitchen be electric? |
| Air conditioning | Is chilled water or AC included, and is it enough for a kitchen? |
| Internet | Which providers serve the building? Card machines, the till and delivery tablets depend on it |
| Waste | Where does rubbish go, and when is it collected? |
| Signage | Where is a sign allowed, and what size? |
| Parking and access | Can customers park and can riders collect easily? |
For the network, Wi-Fi and cabling that the till, card machines, cameras and delivery tablets run on, a specialist installer saves trouble later. [Listonics](https://listonics.com/services/network-and-wifi/) is a Dubai IT company that installs business networks and Wi-Fi.

## Step 7: Plan the team
| Role | What they do | When you need one |
|---|---|---|
| Café manager or working owner | Runs the shift, ordering, rota and cash | From day one |
| Head barista | Sets drink quality, trains others, maintains equipment | Any coffee-led café |
| Baristas | Make drinks and serve | Enough to cover every shift, with days off |
| Cook or chef | Runs the hot kitchen | Any cooked menu |
| Baker or pastry chef | Bakes and finishes pastry | In-house bakery or dessert menu |
| Kitchen helper and steward | Prep, cleaning and wash-up | Any kitchen |
| Floor staff and cashier | Take orders, serve, clear | Table service or busy counters |
| Delivery packer | Packs and hands over app orders | When delivery volume grows |
Three things to remember about staffing in Dubai:
- **Cover, not headcount.** A café open long hours, seven days a week, needs more than one person per station to allow for days off and leave.
- **Visas and training take time.** Staff who handle food need health and training requirements met before they start. See [the approvals guide](https://foodonfocus.com/blog/cafe-licence-and-approvals-dubai/).
- **Hire before opening, not at opening.** The team needs time to learn the menu, the till and each other. They are also needed for the pre-opening photo and video shoot.

## Step 8: List every cost
We do not quote figures here, because they vary too much by location and concept and any number would mislead. What matters is that nothing is missing from the list.
| Group | What to include |
|---|---|
| Property | Rent, often paid in advance; security deposit; agent commission; tenancy registration |
| Licences and approvals | Trade licence, food approvals, fire safety approval, signage permit, renewals |
| Design and fit-out | Designer and drawings, contractor, kitchen extraction, flooring, joinery, lighting, signage, landlord fit-out deposit |
| Equipment | Coffee machine and grinders, ovens, fridges and freezers, dishwasher, furniture, smallwares |
| Utilities | Electricity and water connection and deposits, gas, internet, chilled water |
| Technology | Till or ERP system, card machines, printers, tablets, cameras, website |
| People | Recruitment, visas and medicals, health insurance, uniforms, training, salaries before opening |
| Brand and marketing | Name and logo, menu design, packaging, photography and video, launch campaign |
| Opening stock | Coffee, milk, food ingredients, packaging, cleaning supplies |
| Professional fees | Accounting, tax registration, legal review of the lease |
| Working capital | Several months of rent, salaries and stock while sales build |
For sourced market figures, see our [Dubai restaurant industry statistics](https://foodonfocus.com/blog/dubai-restaurant-industry-statistics/) and [how much a restaurant should spend on marketing](https://foodonfocus.com/blog/restaurant-marketing-budget-dubai/).

## Common planning mistakes
- **Signing the lease before checking power and extraction.**
- **A menu too long for the kitchen.**
- **Too many seats and too little storage.**
- **No space for delivery riders.**
- **Forgetting the rent-free period ends.** Fit-out delays eat into it.
- **No money left for the first three months.**

## Where Food On Focus fits in
We are not architects or licensing consultants. We are a Dubai agency that works only with food and beverage brands, and we handle the brand side of an opening: name and identity, [menu design](https://foodonfocus.com/menu-design-dubai/), packaging, photography and video, and the launch campaign. See our [restaurant launch](https://foodonfocus.com/restaurant-launch-agency-uae/) and [café marketing](https://foodonfocus.com/cafe-marketing-agency-dubai/) services, and continue with [the systems to set up before opening](https://foodonfocus.com/blog/cafe-pos-erp-website-delivery-google-setup-dubai/).

**Related reading:** [restaurant kitchen layout, menu by cuisine and staffing](https://foodonfocus.com/blog/restaurant-kitchen-layout-menu-and-staffing-dubai/).

## Frequently asked questions

### How do I plan a café floor plan?
Start from the menu, list the equipment it needs, then lay out the bar and kitchen so customers and food move in separate paths. Add seating, storage, wash-up, a staff area and accessible utilities. In Dubai the kitchen layout is reviewed as part of the food approvals.

### What should I decide first when opening a café?
The concept and the menu. They decide the equipment, the kitchen size, the number of seats and the team, and therefore which unit will work.

### What is menu engineering?
It is a method of sorting menu items by how well they sell and how much profit each makes, then promoting the profitable best sellers, fixing or repricing the others and removing the weakest.

### How many staff does a small café need?
It depends on the menu and opening hours. A coffee-led café needs trained baristas for every shift plus cover for days off; a cooked menu adds a cook and a kitchen helper. Plan by shifts to cover, not by headcount.

### What utilities should I check before leasing a café unit?
Electrical load, water and drainage points, a grease trap, a route for kitchen extraction, gas availability, air conditioning, internet providers, waste collection, signage rules and access for customers and delivery riders.

### What costs are involved in opening a café in Dubai?
Property, licences and approvals, design and fit-out, equipment, utilities, technology, people and visas, brand and marketing, opening stock, professional fees and working capital for the first months.